Question: At a weekly meeting during the project implementation, the project manager Charlie used the following table to inform everyone of the current progress. According to

At a weekly meeting during the project implementation, the project manager Charlie used the following table to inform everyone of the current progress. According to this table, find the current progress of the project. (20 points) Activity Planned Value Percent Completion Actual Cost Baseline $20000 90% $10000 Detailed Design $50000 90% $60000 Testing $30000 100% $40000