Question: 1 . Below is the table which includes the information of a new project of ABC Inc. Table 1 . Activity Immediate Predecessor ( s

1. Below is the table which includes the information of a new project of ABC Inc.
Table 1.
Activity Immediate
Predecessor(s) Time
(Weeks)
A ---3
B ---5
C A 6
D B 8
E B 5
F C, D 5
G D, E 8
H G, F 9