Question: 1. Below is the table which includes the information of a new project of ABC Inc. Table 1. Activity Immediate Predecessor (s) Time (Weeks) A
1. Below is the table which includes the information of a new project of ABC Inc. Table 1.
| Activity | Immediate Predecessor (s) | Time (Weeks) |
| A | --- | 3 |
| B | --- | 5 |
| C | A | 6 |
| D | B | 8 |
| E | B | 5 |
| F | C, D | 5 |
| G | D, E | 8 |
| H | G, F | 9 |
Please answer the following questions: (1) Draw the network corresponding to the information of Table 1. (2) Determine the critical path and the expected project duration (3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2 with your answer.
| Activity | Earliest Start | Earliest Finish | Latest Start | Latest Finish | Slack |
| A | |||||
| B | |||||
| C | |||||
| D | |||||
| E | |||||
| F | |||||
| G | |||||
| H |