Question: Budget at Completion ( BAC ) $ 4 0 , 0 0 0 Estimate at Completion ( EAC ) $ 3 0 , 0 0

Budget at Completion (BAC) $40,000
Estimate at Completion (EAC) $30,000
Earned Value (EV) $17,000
Actual Cost (AC) $15,000
What is the TCPI (to complete performance index) to meet the current estimate at completion (EAC)? Round to TWO decimal places.