Question: ( FR ) The Actual Costs ( AC ) to date are $ 1 2 , 0 0 0 and the Budget at Completion (
FR The Actual Costs AC to date are $ and the Budget at Completion BAC for a project is $ The Earned Value EV is $ At this stage, the project management team did a manual bottomup summation of costs and forecast an Estimate to Complete ETC of $ What is the Estimate at Completion EAC for the project?