Question: 1. Calculate the minimum required conveyor speed for this example. 8 hour shift, 45 minutes downtime, 90% performance, 3100 units per shift and each unit
1. Calculate the minimum required conveyor speed for this example. 8 hour shift, 45 minutes downtime, 90% performance, 3100 units per shift and each unit is 33" long.
a.23 ft/min
b.21 ft/min
c. 22 ft/min
d. 24 ft /min
2.Given the takt time or R value of .405, balance the following line. The efficiency of this line is closest to:
| Operation | Time Std. |
| 1 | .455 |
| 2 | .813 |
| 3 | .233 |
| 4 | .081 |
| 5 | .945 |
Group of answer choices
a.81%
b.83%
c. 82%
d. 80%