Question: 1. Complete a table (similar to the example video e) that shows the Activity, EST (Earliest Start Time), and LST (Latest Start Time), and Slack.


1. Complete a table (similar to the example video e) that shows the Activity, EST (Earliest Start Time), and LST (Latest Start Time), and Slack. 2. Find the critical path. What is the minimum time the project will take to complete (days)? Arrows for those who need it: 5 2 E 3 3 3 START @?@ F 0 O FIN 2 2 N G co M Activities Latest Start Time Earliest Start Time Slack A B D E F G H 1 J L