Question: . Below is the table which includes the information of a new project of ABC Inc. Table 1. Activity Immediate Predecessor(s) Time (Weeks) A ---
. Below is the table which includes the information of a new project of ABC Inc.
Table 1.
| Activity | Immediate Predecessor(s) | Time (Weeks) |
| A | --- | 3 |
| B | --- | 5 |
| C | A | 6 |
| D | B | 7 |
| E | B | 5 |
| F | C, D | 5 |
| G | D, E | 8 |
| H | G, F | 9 |
Please answer the following questions:
(1) Draw the network corresponding to the information of Table 1.
(2) Determine the critical path and the expected project duration
(3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2 with your answer.