Question: . Below is the table which includes the information of a new project of ABC Inc. Table 1. Activity Immediate Predecessor(s) Time (Weeks) A ---

. Below is the table which includes the information of a new project of ABC Inc.

Table 1.

Activity

Immediate

Predecessor(s)

Time

(Weeks)

A --- 3
B --- 5
C A 6
D B 7
E B 5
F C, D 5
G D, E 8
H G, F 9

Please answer the following questions:

(1) Draw the network corresponding to the information of Table 1.

(2) Determine the critical path and the expected project duration

(3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2 with your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!