Question: 1- Consider the following project schedule: Activity A B C D E F G Immediate Predecesso Most r Optimistic probable Pessimistic -1 2 3 -2

1- Consider the following project schedule: Activity A B C D E F G Immediate Predecesso Most r Optimistic probable Pessimistic -1 2 3 -2 3 4 A 4 5 6 B 8 9 10 C 2 5 8 B 4 5 6 E 1 2 3 Determine the expected time, earliest time, latest start, finish times and variance for each activity. Also determine the critical path and expected project completion time. 2- True or False: PERT is a probabilistic technique in quantitative analysis

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!