Question: 1. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M N O Probable 10 8 6 Pessimistic 15 9

1. Consider the network described in the table
1. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M N O Probable 10 8 6 Pessimistic 15 9 10 3 9 10 10 J J KM KM LN Optimistic 8 7 5 3 1 4 3 3 5 7 8 P a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer than 30 time units