Question: 1. Consider the tasks, durations, predecessors, and durations in the table below. Draw the project network. Identify the critical path(s) and the project completion time.
1. Consider the tasks, durations, predecessors, and durations in the table below.
- Draw the project network.
- Identify the critical path(s) and the project completion time.
| Activity | Immediate Predecessor | Time in days |
| A | - | 4 |
| B | A | 4 |
| C | B | 5 |
| D | B | 3 |
| E | C,D | 6 |
| F | E | 5 |