Question: 1. Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path

1. Considering the following project data in the

1. Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method). The actual proaress and cost are recorded at the end of 15th week. a) Give the planned value of the project.(Requirement: give the cost of every week during the project planned duration, and plot the accrued planned value) b) According to the actual progress and cost data, calculate the SV,SPI,CV,CPI, and explain the meaning of these indicators. c) According to the actual progress data, calculate the ES,SV(t),SPI(t), and explain the meaning of these indicators

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!