Question: Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method).

Considering the following project data in the table. Assuming that in the baseline schedule every activity stars at the early start time (critical path method). The actual progress and cost are recorded at the end of 15th week.

activity

Duration(week)

cost

completed

Actual cost

successors

1

0

0

0

0

2,3,4

2

6

120

100%

160

9,10

3

4

76

100%

70

5,6,7

4

3

30

100%

46

8,11

5

1

46

100%

76

10

6

6

150

100%

180

12

7

8

230

80%

220

8,11

8

5

186

10%

40

13

9

10

160

75%

180

14

10

12

320

40%

100

12

11

6

248

0

0

12

12

5

137

0

0

13

13

8

268

0

0

14

14

0

0

0

0

Give the planned value of the project.(Requirement: give the cost of every week during the project planned duration, and plot the accrued planned value)

According to the actual progress and cost data, calculate the SV, SPI, CV, CPI , and explain the meaning of these indicators.

According to the actual progress data, calculate the ES, SV(t), SPI(t), and explain the meaning of these indicators.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!