Question: 1. Construct a project Network. 2. Perform Forward and Backward Pass. 3. Determine Project Completion Time. 4. Calculate Slack values. Activity Predecessor Duration (Weeks) A
1. Construct a project Network. 2. Perform Forward and Backward Pass. 3. Determine Project Completion Time. 4. Calculate Slack values. Activity Predecessor Duration (Weeks) A - 3 B A 4 C A 2 D B 5 E C 1 F C 2 G D, E 4 H F, G 3 5. State the Critical Path