Question: 1. Construct a project Network. 2. Perform Forward and Backward Pass. 3. Determine Project Completion Time. 4. Calculate Slack values. Activity Predecessor Duration (Weeks) A

1. Construct a project Network. 2. Perform Forward and Backward Pass. 3. Determine Project Completion Time. 4. Calculate Slack values. Activity Predecessor Duration (Weeks) A - 3 B A 4 C A 2 D B 5 E C 1 F C 2 G D, E 4 H F, G 3 5. State the Critical Path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!