Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
| ID | Description | Predecessor | Time |
| A | Survey site | None | 3 |
| B | Excavate site | A | 3 |
| C | Install power lines | B | 4 |
| D | Install drainage | B | 3 |
| E | Pour foundation | C, D | 3 |
|
| |||
1). The project will take _____ days.
2). The critical path is______.
3). The late start on activity C is_________days.
4). The slack on activity C is________ days.
5). The slack on activity D is________ days.
6). The early start on activity E is______ days.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts