Question: 1 . Construct a Project Network Time left 0 : 4 9 : 2 6 2 . Perform Forward and Backward Pass work assig... 3

1. Construct a Project Network
Time left 0:49:26
2. Perform Forward and Backward Pass
work assig...
3. Determine Project Completion Time
4. Calculate Slack Values
ework assig...
5. State the Critical Path
mework assig...
Write down the five answers in the blank space and submit Excel.
mework assig...
ACTIVITY
DESCRIPTION
TIME (WEEKS)
IMMEDIATE PREDECESSORS
A
Build internal components
2
signment 2(2
B
Modify roof and floor
3
C
Construct collection stack
2
A
D
Pour concrete and install frame
4
A. B
E
Build high-temperature burner
4
C
art 2-Calculative
F
install pollution control system
3
C
Part 2 Submit you....
G
Install air pollution device
5
D. E
H
Inspect and test
2
F. G
st-Apr 16,2024

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!