Question: 1. Critical Path Analysis (CPA): Considering the project information presented in the table below: {Total 30 marks Predecessor Activities A B D E F G

1. Critical Path Analysis (CPA): Considering the project information presented in the table below: {Total 30 marks Predecessor Activities A B D E F G H 1 J Duration (days) 4 5 7 6 5 4 5 3 2 4 3 A B D D E F G I, H C,J a. Draw the network diagram b. Calculate the total duration of the project C. Identify the critical path of the project d. Why is it important for project manager to perform a CPA at the early stages of a project [5 Marks] [5 Marks] [5 Marks] (15 Marks]