Question: 1. Critical Path Analysis (CPA): Considering the project information presented in the table below: a. Draw the network diagram (5 marks) b. Calculate the total

1. Critical Path Analysis (CPA): Considering the

1. Critical Path Analysis (CPA): Considering the project information presented in the table below: a. Draw the network diagram (5 marks) b. Calculate the total duration of the project (5 marks) c. Identify the critical path of the project (5 marks) Predecessor Duration (days) 3 4 7 4 Activities A B D E F G H 1 LO 4 5 3 6 A A B B C F G D, E I, H J 4 d. Differential between recourse levelling and resource smoothing (15 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!