Question: 1. Critical Path Analysis (CPA): Considering the project information presented in the table below: a. Draw the network diagram (5 marks) b. Calculate the total

1. Critical Path Analysis (CPA): Considering the

1. Critical Path Analysis (CPA): Considering the project information presented in the table below: a. Draw the network diagram (5 marks) b. Calculate the total duration of the project (5 marks) C. Identify the critical path of the project (5 marks) Predecessor Duration (days) 4 5 7 A B Activities A B D E F G H 1 J K 5 4 5 3 2 4 3 D D E F G I, H C, J d. Why is it important for project manager to perform a CPA at the early stages of a project (15 marks)