Question: Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices. ACTIVITY DURATION PREDECESSORS ES EF LS LF
Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices.
| ACTIVITY | DURATION | PREDECESSORS | ES | EF | LS | LF | TOTAL SLACK |
| A. Design Process Requirements | 2 | --- |
|
|
|
|
|
| B. Benchmark Competitors Processes | 4 | A |
|
|
|
|
|
| C. Prepare Benchmark Report | 1 | B |
|
|
|
|
|
| D. Design Process and Layout | 2 | A |
|
|
|
|
|
| E. Finalize design and setup manf. Cell | 2 | C, D |
|
|
|
|
|
| F. Select and train operators | 1 | D |
|
|
|
|
|
| G. Pilot test new process | 2 | E, F |
|
|
|
|
|
| H. Finalize process design | 1 | G |
|
|
|
|
|
Draw a network diagram.
Identify the ES, EF, LS, LF and slack times in the table using the critical path method.
During the initial stages of the project, a new set of requirements were discovered that would extend the process and layout design activity from 2 to 6 months. The operations group which initiated these requirement changes argues that they would not impact the project duration. Is this true? Justify your answer.