Question: 1. Determine a line balance using the lowest possible cycle time. 2. The workstation utilization rate is : 3. Total idle time : 5: The

1. Determine a line balance using the lowest possible cycle time.
2. The workstation utilization rate is :
3. Total idle time :
5: The production rate :
6. In your own words, for the production line in the Problem if you have to increase the production rate by 20%, what will be your strategy to achieve this increase and why?
Problem 5 (4.0 pt) Consider the assembly line balancing problem shown in the network below. The demand is 64 units per day, and the productive time is 960 minutes per day. Use the positional weight ranking method to complete the line balancing in this problem. 5 8 B D 1 10 3 8 A G H K 7 5 6 C E JStep by Step Solution