Question: 1. Determine each tasks':a. Early start and early finish datesb. Late start and finish dates2. Calculate the float for each task3. Identify the critical path

1. Determine each tasks':a. Early start and early finish datesb. Late start and finish dates2. Calculate the float for each task3. Identify the critical path and the total days for the path4. If activity E changes from 5 days to 10 days, what is the impact on the critical path and total duration of the project? 5. Activity Predecessor ES Duration EF LF LS FLOATA. Start B. A CD. A EF. AGH(end).

1. Determine each tasks':a. Early start and early finish datesb. Late start

C Question 1: 16 A I w

Step by Step Solution