Question: 1. Develop a precedence notation network for the following set of activities. Predecessors Activity Duration A 22 . 10 13 D 8 E 15 F

1. Develop a precedence notation network for the

1. Develop a precedence notation network for the following set of activities. Predecessors Activity Duration A 22 . 10 13 D 8 E 15 F 17 G 15 H 6 I 11 J 12 K 20 A A B.C B,C D.E F F G.H G,H,I HIJ U 2. Determine the following: a. The minimum project duration. b. The Critical Path. c. The total float for each activity. d. The free float for each activity