Question: 1 . Draw the Network Diagram. 2 . Use two - pass method to calculate and show the early and late starts and slack for

1. Draw the Network Diagram.
2. Use two-pass method to calculate and show the early and late starts and slack for each activity.
3. Using the Enumeration Method list all the network paths with length. (i.e. A-B-C-D =12)
4. What is the Critical Path? How do you know it is the CP?
Activity Details Duration (days) Predecessor(s)
A Dig Holes 3-
B Buy Wood 2 Dig Holes
C Buy Gate 1 Dig Holes
D Erect Fence 3 Buy Wood
E Buy Paint 1 Buy Gate
F Erect Gate 1 Erect Fence, Buy Paint
G Paint Fence 2 Erect Gate
H Paint Gate 1 Paint Fence