Question: By using the following table answer questions: - Activity Duration (days) Predecessor(s) A 2 3 4 A,B D 5 C E 2 D F. 3

 By using the following table answer questions: - Activity Duration (days)

By using the following table answer questions: - Activity Duration (days) Predecessor(s) A 2 3 4 A,B D 5 C E 2 D F. 3 D G E H 2 F I 2 GH 1. Draw the Network Diagram 2. Determine the Critical Path and duration of the project (in days). 3. By using a table determine only the total slack of each task. 4. By using a drawing calculate early and late start and finished dates for each task (ES, EF, LS, LF)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!