Question: Spring Project Management (IE 310) Summer-2021 In-Class Exercise 1 A network consists of the activities in the following list. Times are given in wecks. Activity

Spring Project Management (IE 310) Summer-2021
Spring Project Management (IE 310) Summer-2021 In-Class Exercise 1 A network consists of the activities in the following list. Times are given in wecks. Activity Preceding Time A 3 B 6 2 11 D B AD E F 4 7 G EF 9 1. Draw the network diagram 2. Calculate the ES, EF, LS, LF, and slack for each activity 3. What is the critical path? 4. What is the project completion time? Results Task Early Start Early Finish Late Start Late Finish Slack B D E F G