Question: 1 . Explain the terms: critical path, critical activities. 2 . The following are the time estimates and the precedence relationships of the activities in
Explain the terms: critical path, critical activities.
The following are the time estimates and the precedence relationships
of the activities in a project network:tableActivitytableIMMEDIATEPredecessorActivitytabletime estimateweeksABCADBEBFCGEHDIF GJH I,K
Draw the project network diagram. Determine the critical path and the project completion time.