Question: 1 . Explain the terms: critical path, critical activities. 2 . The following are the time estimates and the precedence relationships of the activities in

1. Explain the terms: critical path, critical activities.
2. The following are the time estimates and the precedence relationships
of the activities in a project network:\table[[Activity,\table[[IMMEDIATE],[Predecessor],[Activity]],\table[[time estimate],[(weeks)]]],[A,-,4],[B,-,7],[C,A,3],[D,B,6],[E,B,4],[F,C,7],[G,E,6],[H,D,10],[I,F, G,3],[J,H, I,4],[K,,]]
Draw the project network diagram. Determine the critical path and the project completion time.