Question: 1. find the critical path and expected project completion time 2. what is the probability of completion the project on or before 20 weeks? Group

1. find the critical path and expected project completion time
2. what is the probability of completion the project on or before 20 weeks?  1. find the critical path and expected project completion time 2.

Group 2 Most likely Activity Variance Predecessors optimistic Pessimistic Expected Time (t) b o m a 2 5 8 1 5 3 2 0.11 2 B 1 - 4 7 1 4 1 6 4 0.44 4 D 2 2 9 3 E 1 B 1.77 2.77 6 14 7 F 4 B 3 3 4 0.11 G 2 DE 2 3 N 0.11 H F 1 4 7 4 1 1 CGH