Question: asap plz Activity Predecessor Duration (weeks) optimistic Most likely Pessimisti. 5 6 3 B 1 1 7 5 7 4 D 1 2 3 E

asap plz Activity Predecessor Duration (weeks)

asap plz

Activity Predecessor Duration (weeks) optimistic Most likely Pessimisti. 5 6 3 B 1 1 7 5 7 4 D 1 2 3 E B 9 2 5 9 F G H sunmaa 009 00 00 1 1 2 4 C 2 8 NUNUN 10 I EF D HG 8 2 2 J 8 a) Construct the project network. b) Find the expected duration and variance of each activity. c) Find the critical path and expected project completion time. d) What is the probability of completing the project on or before 22 weeks. m

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!