Question: 1. Finish the table, adding a column for Early Start Time, Early Finish Time, Late Finish, Late Start and Slack. Find the critical path. 2.

1. Finish the table, adding a column for Early Start Time, Early Finish Time, Late Finish, Late Start and Slack. Find the critical path.

2. Draw a project management workflow diagram that outline the flow of work

Task Immidiate Predecesor Immidiate Successor Activity Duration
A B 1 Hour
B A C 1 Hour
C B D, E 1 Hour
D C K 5 Hours
E C F 7 Hours
F E K 2 Days
G B H 5 Hours
H B I 2 Days
I G,H J 3 Hours
J G,H,I K 3 Hours
K E,J L 5 Hours
L K M 1 Hour
M K, B, H N 1 Hour
N M O 2 Days
O N P 1 Day
P O 1 Day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!