Question: 1. Finish the table, adding a column for Early Start Time, Early Finish Time, Late Finish, Late Start and Slack. Find the critical path. 2.
1. Finish the table, adding a column for Early Start Time, Early Finish Time, Late Finish, Late Start and Slack. Find the critical path.
2. Draw a project management workflow diagram that outline the flow of work
| Task | Immidiate Predecesor | Immidiate Successor | Activity Duration |
| A | B | 1 Hour | |
| B | A | C | 1 Hour |
| C | B | D, E | 1 Hour |
| D | C | K | 5 Hours |
| E | C | F | 7 Hours |
| F | E | K | 2 Days |
| G | B | H | 5 Hours |
| H | B | I | 2 Days |
| I | G,H | J | 3 Hours |
| J | G,H,I | K | 3 Hours |
| K | E,J | L | 5 Hours |
| L | K | M | 1 Hour |
| M | K, B, H | N | 1 Hour |
| N | M | O | 2 Days |
| O | N | P | 1 Day |
| P | O | 1 Day |