Question: 1) Given the following information for a one-year project, answer the following questions. (Please show your work each question) Planned Value (PV) = $23,000 Earned
1) Given the following information for a one-year project, answer the following questions. (Please show your work each question)
Planned Value (PV) = $23,000
Earned Value (EV) = $20,000
Actual Cost (AC) = $25,000
Budget At Completion (BAC) = $120,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? IS it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Us the SPI to estimate how long it will take to finish this project.
e. Sketch the earned value chart for this project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
