1- Given the following network:
a) Find the earliest time the project will be completed.
b) Find the critical path..
c) If activity I is delayed by 5 days, find the completion time of the entire project.
Activity t G
A13
B9A
C14EH
D6C
E6D
F11
G10BFI
H9
I10