Question: (1) Given the network shown, what is the earliest start time for activity F ? A. 6 B. 8 C. 10 D. 13 E. 16

(1) Given the network shown, what is the earliest
(1) Given the network shown, what is the earliest start time for activity F ? A. 6 B. 8 C. 10 D. 13 E. 16 (2) Given the network shown, what is the latest finish time for activity B? A. 5 B. 8 C. 10 D. 11 E. 13 (3) Given the network shown, what is the slack time for activity D? A. 1 B. 2 C. 3 D. 4 E. 5