Question: help (1) Given the network shown, what is the earliest start time for activity F ? A. 6 B. 8 C. 10 D. 13 E.
help
(1) Given the network shown, what is the earliest start time for activity F ? A. 6 B. 8 C. 10 D. 13 E. 16 (3) Given the network shown, what is the slack time for (2) Given the network shown, what is the latest finish time activity D? for activity B ? A. 1 A. 5 B. 2 B. 8 . C. 3 C. 10 D. 4 D. 11 E. 5 E. 13