Question: 1. How are schedules planned in adaptive project? Rolling wave planning at the start of each iteration that determines how much of the backlog to

1. How are schedules planned in adaptive project?

  • Rolling wave planning at the start of each iteration that determines how much of the backlog to deliver in the iteration
  • Waterfall planning at the start of each iteration that determines how much of the backlog to deliver in the iteration
  • Waterfall planning used to deliver incremental value at the end of each iteration
  • Rolling wave planning used to accumulate and deliver value at the end of the project