Question: 1. identify the critical path and project time. 2. determine the total minimum cost to crash this project to 23 weeks. indicate which activities you
1. identify the critical path and project time. 2. determine the total minimum cost to crash this project to 23 weeks. indicate which activities you will be crashing, by how much weeks each, and what additional cost of crashing will be.

allowing information is available for Triple Project Corp.: Crash Time Normal Time (weeks) Normal Cost Crash Cost Crash Cost per Week (weeks) $800 $1,200 $200 6 $500 $725 $225 9 $800 $950 $75 10 $800 $850 $50 10 $500 $800 $100 3 $600 $750 $150 6 $900 $990 $30 C D G B
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
