Question: For the network shown: a . List ES , EF , LS , LF , and Slack for all activities on the network and identify

For the network shown:
a. List ES, EF, LS, LF, and Slack for all activities on the network and identify the critical path and
completion time. (6pt)
b. For the indirect cost, if the project can be finished in 26 days, it is $4500; if the project can be
finished in 25 days, it is $4200; if the project can be finished in 24 days, it is $3900; if the project
can be finished in 23 days, it is $3600; if the project can be finished in 22 days, it is $3200; if the
project can be finished in 21 days, it is $2700.
For the time and direct cost data shown below, reduce the project completion time by three days.
Assume a linear cost per week shortened, and show, STEP bv STEP, how you arrived at your
schedule. What is the new total cost after crashing the project by three days? What is the new
critical path after crashing the project? (9pt)
 For the network shown: a. List ES, EF, LS, LF, and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!