Question: For the network shown: a . List ES , EF , LS , LF , and Slack for all activities on the network and identify
For the network shown:
a List ES EF LS LF and Slack for all activities on the network and identify the critical path and
completion time. pt
b For the indirect cost, if the project can be finished in days, it is $; if the project can be
finished in days, it is $; if the project can be finished in days, it is $; if the project
can be finished in days, it is $; if the project can be finished in days, it is $; if the
project can be finished in days, it is $
For the time and direct cost data shown below, reduce the project completion time by three days.
Assume a linear cost per week shortened, and show, STEP bv STEP, how you arrived at your
schedule. What is the new total cost after crashing the project by three days? What is the new
critical path after crashing the project? pt
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock