Question: 1. If a critical path task has an early start of 2 days and duration of 5 days what is its slack? Select one or
1. If a critical path task has an early start of 2 days and duration of 5 days what is its slack? Select one or more: a. 3 b. 10 c. 7 d. 0 e. none of these
9. Theoretically, a linear production line cannot operate at a cycle time shorter than the length of the longest task. Select one: True False
6. An automobile is normally created with a process layout. Select one: True False
11. Which of the following statements is (are) true? I Effective capacity of a system is expected to be GREATER than its design capacity. II. When determining a break even quantity, if your answer is a decimal, then you should round the number up. III. A waiting line is also known as a queue. Select one or more: a. II and III b. III only c. I and II d. I only e. I, II, and III