Question: 1) If a process was sampled hourly for the past 30 hours with a sample mean size of 4 and then mean of the 30

1) If a process was sampled hourly for the past 30 hours with a sample mean size of 4 and then mean of the 30 samples was 52.43 and the mean of the 30 rages was 3.45

A- What would the UCL and LCL be for the range chart?

B- What is the standard deviation?

C- If the specifications for the process was 50 plus or minus 7, draw a sketch of the process distribution with the specifications limits labeled.

D- find the Cpk

E. what would be the capability index if the process was centered (Cp)

F. What would the process be capable of 3 sigma quality if the process was centered?

G- would the process be 6sigma capable with specifications if the process was centered?

THIS IS ALL PART OF ONE QUESTION-- ALL PARTS NEED TO BE ANSWERED!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!