Question: 1. If a project is over cost or behind schedule, its Project Percent Complete Index (PPCI) will be: Group of answer choices a value greater
1. If a project is over cost or behind schedule, its Project Percent Complete Index (PPCI) will be:
Group of answer choices
a value greater than 1.00
exactly 1.00
a value less than 1.00
a value that is always negative (below zero)
none of the above
2.
Which of the following is NOT a consideration in structuring a project monitoring information system?
Group of answer choices
what data will be collected
what analysis and processing will be performed on the data
what reports will be generated
the frequency of report generation
the ability of the system to monitor continuous operations (non-project activities) in the organization
3.
The comparison of actual project performance against specifications found in the scope statement and/or work package documentation for the purpose of seeing if the project is delivering what it is supposed to deliver, is called:
Group of answer choices
technical performance
schedule performance
budget performance
detection performance
comprehensive performance
4.
To guard against the situation known as Scope Creep, it is important to have:
Group of answer choices
protective screenings during the human resources departments hiring activities
strong scope definition
an excellent change management system
both a and b
both b and c
5.
Forecasting final project costs:
Group of answer choices
may be important for quoting or updating prices for project customers and stakeholders
may become necessary as the project goes along, due to availability of new information
may never be performed after the original baseline duration and costs have been locked in prior to the start of the project
both a and b
both b and c