Question: If a project is over cost or behind schedule, its Project Percent Complete Index ( PPCI ) will be: a value greater than 1 .
If a project is over cost or behind schedule, its Project Percent Complete Index PPCI will be:
a value greater than
exactly
a value less than
a value that is always negative below zero
none of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
