Question: If a project is over cost or behind schedule, its Project Percent Complete Index ( PPCI ) will be: a value greater than 1 .

If a project is over cost or behind schedule, its Project Percent Complete Index (PPCI) will be:
a value greater than 1.00
exactly 1.00
a value less than 1.00
a value that is always negative (below zero)
none of the above