Question: 1. If you cannot provide a Master Production Schedule (MPS) as an input file, you cannot run a material requirements planning (MRP) system. A. True
1. If you cannot provide a Master Production Schedule (MPS) as an input file, you cannot run a material requirements planning (MRP) system.
A. True
B. False
2. Which of the following most closely describes independent demand
A. Demand for component parts
B. Scheduled receipts
C. Components held by suppliers
D. Estimates parameters of the ordinary least squares
E. Demand for end items/finished goods