Question: 1 . In the site development process approximately 4 0 0 , 0 0 0 bcy of soil material ( sandy clay ) must be
In the site development process approximately bcy of soil material sandy clay must be cut from one area in a new shopping mall site and used as fill in another area. The average distance between cut and fill is ft Which of the following equipment items is best for this work?
a Scrapers
b Dozers with Universal Blade
c Hoe and onroad dump trucks
d Loader and offroad dump trucks
Tiltup panels are typically cast on the building floor slab. Which of the following is a possible disadvantage of this method?
a Hoisting the panels requires a mobile crane
b Casting beds are not required
c Floor may be scarred
d A panel placement map is used to draw the panels on the slab
Which of the following is most likely suggested when highly variable subsurface conditions will be encountered?
a Prestressed concrete piles
b Auger cast piles
c Sheet piles
d Steel H piles
Which of the following is NOT true about highway plans?
a Plan view is formed by looking down from above and profile view is formed by looking from side
b In cross section views, existing conditions are shown with dotted lines and new work is shown with a solid line
c Cross section view is formed by looking at section through the road
d Distances along the roadway are indicated by station number. The distance between stations is ft
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock