Question: Schurz Corporation's management reports that its average delivery cycle time is 23 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency
Schurz Corporation's management reports that its average delivery cycle time is 23 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency (MCE) is 0.40, its average move time is 0.6 day, and its average queue time is 2.0 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.) a. Wait time b. Process time c. Inspection time days days days
Step by Step Solution
3.49 Rating (152 Votes )
There are 3 Steps involved in it
a Wait Time Wait Time Average Delivery Cycle Time Average Throughput Time Wait Tim... View full answer