Question: is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. Select one: a . Analogous estimating b . Bottom

is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
Select one:
a. Analogous estimating
b. Bottom-Up estimating
c. Parametric estimating
d. Earned Value Management
 is a methodology that combines scope, schedule, and resource measurements to