Question: 1. Perform financial analysis for a project using the format discussed in the course. Assume the projected costs and benefits for this project are spread
1. Perform financial analysis for a project using the format discussed in the course. Assume the projected costs and benefits for this project are spread over four years as follows: Estimated costs are $130,000 in Year 1 and $15,000 each year in Years 2, 3, 4, and 5. Estimated benefits are $0 in Year 1 and $90,000 each year in Years 2, 3, 4, and 5. Use an 8% discount rate. Use the NPV template provided (modify to suit your answer) and clearly display the NPV, ROI, and year in which payback occurs. Write a paragraph explaining whether you would recommend investing in this project based on your financial analysis. Explain your answer referring to the NPV, ROI, and payback for this project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts