Question: 1. Please use the critical path method to determine which path is the critical path of the project shown above. a. A-B-G-H-J b. A-C-G-H-J c.

1. Please use the critical path method to determine which path is the critical path of the project shown above.
a. A-B-G-H-J
b. A-C-G-H-J
c. A-C-E-I-J
d. A-D-F-I-J
Please use the AON diagram to answer Q2 to 08. 1 units time = 1 day. B4 G4 H5 A2 C5 E4 J 1 13 D7 F 3 3Step by Step Solution