Question: 1 po Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3. its succeeding activity, Task E, has a

1 po Calculate the latest start for Task B if its
1 po Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3. its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 3 days. O day 5 O day 3 O day 7 O day 4