Question: Calculate the earliest start for Task B if its predecessor, Task A , finishes on day 5 and the duration of Task B is 3

"Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 5 and the duration of Task B is 3 days."
Question 15 options:
Day 8
Day 5
Not able to calculate
Day 2