Question: Calculate the latest start for Task B if its predecessor, Task A , finishes on day 3 , its succeeding activity, Task E , has

Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.a) day 5b) day 3c) day 7d) Cannot be calculated based upon information given.